Projects

Transport of Bulk Material

Consolidated delivered 45,000T of ballast from a quarry to a major Perth road extension project.

Decarbonisation Strategy Project

For this project we explored how to ensure Consolidated Group is working towards a greener future by developing a decarbonisation plan for 2023 - 2030.

Ballast Screening Project

For this project we transported ballast for a major project in Perth. We then screened it for repurposing using our screening unit and then transported it back to the project. This project ran for two months and we screened over 10,000T of ballast.

Bulk Lithium Transport

Transport of lithium from Greenbushes mine to Bunbury Port with 6 trucks running 24/7 for Qube. Additional training and inductions were needed for drivers to be able to access the various restricted sites and we mobilised them quickly and professionally. This job is ongoing.

Oversize Moves

Transport of oversize units, machines, conveyor belts and various other items to the Pilbara. Each oversize move required a permit from Main Roads and all specifications of this specialised permit were adhered to. We have a large cohort of experienced long haul oversized drives and have them readily available at short notice.

City of Rockingham

Bulk cartage of waste sand from dredging sand (103500m) from Point Peron to Miller Road land fill facility to be utilised as capping. To transport the bulk material our team loaded 10 trucks on a constant rotation to the land fill facility and return. We had to engage local road users to set transport route and work around peak periods and school zones.

City of Rockingham

Construct various limestone track for the DFS in conjunction with city of Rockingham Successfully transport 9500 tonnes of limestone from Miller Road quarry to the job site. Given the tight access we had to use semi tippers and 6 wheelers to ferry down the access point. Traffic management and stockpile locations were implemented in each area.

Acciona

Kwinana KWTE. Construct a basin, piling pads and detailed earth works for installation of earthing cables and concrete blinding. Creating 4 piling pads on the inner side of the basin for piling works to be conducted. Remove, transport and dispose of 12,000m3 of waste material.

CPB Contractors

Metro Net Yanchep / Thornlie Cockburn link. Supply of water carts, 6x4 end tippers, articulated haul trucks, semi tippers/side tippers, graders, rollers, skid steers, excavators and wheel loaders as required with both wet and dry hire options. Currently we are supplying both Thornlie Cockburn Link and Yanchep Rail Extension with ongoing monthly service.