Acciona

DATES 

2020

PROJECT DESCRIPTION 

Kwinana KWTE 

Construct a basin, piling pads and detailed earth works for installation of earthing cables and concrete blinding. Creating 4 piling pads on the inner side of the basin for piling works to be conducted. Remove, transport and dispose of 12 000m3 of waste material.